OPUS Projects question
I have borrowed two R10s, that gives me 4 receivers. I am planning on running an OPUS Projects session tomorrow and it has been a while since I did one. I will be leaving one stationary and moving the other three around. At one time there was talk about using shorter sessions and OPUS RS but I can’t find anything saying NGS ever implemented that. Assuming everything must go thru OPUS S, that is 2 hours minimum.
Now my question, Do I need to have the same 2 hours on the three receivers that will be moved or can they be staggered?
In other words, Do I move all three and when I get the last one started logging, THEN start timing 2 hours and a few minutes?
I can’t find my notes and it has been almost three years. I expect this to take about 12 hours.
Thanks, James